Quick answer: For building permits in Ontario, aim to submit a complete application in winter if you want to start construction in spring. A qualifying house application generally has a 10-business-day decision period, but zoning checks, drawings, separate approvals, and revisions can add time. Work backward from your target start date and allow room for each step.
An April start for a rear addition might depend on a question you can answer in December. Does the proposed addition fit within the setbacks for your lot? If it needs to move or shrink, your building designer may need to update the floor plans and coordinate changes with the structural engineer before you apply.
That’s the advantage of starting in winter. You have time to resolve questions while the plans are still on paper. For homeowners planning custom homes, additions, or major renovations in Mississauga and surrounding Ontario communities, Leedway Group can help coordinate design and approvals through its design-build services. Leedway Group
What does the Ontario building permit timeline cover?
Ontario’s prescribed timeline covers the municipality’s decision on an application that meets the Building Code requirements for completeness. Depending on the building category, the period is generally 10, 15, 20, or 30 business days. Your project schedule also needs time to prepare the application and address any issues the municipality identifies. ontario.ca
| Building category | Decision period for a qualifying complete application |
|---|---|
| House | 10 business days |
| Small building | 15 business days |
| Large building | 20 business days |
| Complex building | 30 business days |
Ask your building department which category applies to your project. “Small building” is a Building Code category, so the everyday size of your renovation may give you the wrong impression. Under the Building Code Act, the prescribed period is for a decision to issue or refuse the permit. If the municipality refuses the application, it must provide its reasons. Ontario’s Building Code Act.
How early should you apply for an Ontario building permit?
If you’re aiming for an April or May start, use December or January to check the property and prepare drawings. Submit as soon as the package is complete. A project that needs a minor variance or another approval may need an earlier start, since that process can affect when you can submit a qualifying application. ontario.ca
December or January | Check the zoning bylaw
Start with your property address and a sketch of the work. Ask municipal planning staff which zoning rules apply and whether a preliminary review is available. For an addition, check the distance to the property lines, the proposed height, and how much of the lot the finished building would cover. Ask whether any other approvals apply to the site, such as heritage or conservation authority approval. Ontario’s guide to building permits.

January or February | Coordinate the building code drawings
Give your building designer the municipality’s checklist and confirm who will prepare each part of the package. Depending on the project, that could include a site plan, floor plans, elevations, building sections, and structural details. A useful check before submission is to compare dimensions across the drawings. If a rear wall moves on the floor plan, check that the site plan and foundation drawings reflect the same change. Ontario’s Building Code Compendium.
February or March | Allow time for a resubmission
Once you submit, confirm that the municipality has everything it needs and ask when it considers the application complete. If the examiner requests changes, have one person track the comments and coordinate the response. For example, a request to clarify how a new beam is supported might require changes on both the architectural and structural sheets. Send the coordinated drawings together and ask the municipality how it handles revised submissions. ontario.ca

Before the spring start | Confirm the schedule with your general contractor
While the application is under review, your general contractor can check trade availability, plan site access, and flag materials with long lead times. Keep the start date tentative until the required permit is issued. Once it’s in hand, review the approved drawings together and confirm who will request inspections before work reaches stages that need sign-off. ontario.ca
What can push a spring start back?
A spring start can slip before the formal permit review even begins. An unresolved setback, a missing structural detail, or a separate approval can hold up the application. Give those items dates on your project schedule so you can see early which one is most likely to affect construction. ontario.ca
Consider a homeowner targeting mid-April for a rear addition. In January, the designer finds the proposed footprint sits too close to the lot line. If the homeowner accepts a shallower addition that meets the setback, the designer can revise the plans and move toward submission. If the homeowner wants to keep the original footprint and pursue a minor variance, the schedule needs room for that separate process and its outcome. Both options affect the build in different ways, so decide before booking excavation. ontario.ca
Frequently asked questions
1. Can I apply for a building permit in Ontario during winter?
Yes. Check your municipality’s submission process, holiday hours, and project checklist. Winter gives you extra calendar time to resolve comments or finish approvals before your preferred spring start. The prescribed decision period still depends on the application meeting the Building Code requirements. ontario.ca
2. Does a complete house application mean I’ll have a permit in 10 business days?
The 10-business-day period is generally for a decision on a qualifying complete application in the house category. The decision may be to issue or refuse the permit. Confirm that your project falls in this category and ask when the decision period begins. ontario.ca
3. What should I have ready before submitting my application?
Use your municipality’s checklist for the specific work. Confirm whether it calls for:
- Application forms and permit fees
- A site plan and construction drawings
- Designer information or engineering documents, where required
- Evidence of any separate approvals that apply to the property
Ontario’s guide to building permits.
4. Can my contractor start demolition while the permit is under review?
Ask the municipality whether the proposed demolition requires a permit. If it does, wait until the permit is issued before starting that work. Describe exactly what you plan to remove so the building department can advise you based on the scope. ontario.ca
5. What happens if the municipality asks for revised drawings?
Ask your designer to respond to each comment and update every affected drawing. Include a short note showing where each change appears. Before you revise the construction date, ask the municipality to confirm the resubmission process and expected next steps for your file.
Conclusion
For a spring construction start in Ontario, use winter to check zoning, complete the drawings, and submit the permit application with time for revisions. Work backward from the date you want your crew on site. If the property needs a separate approval, put that step on the schedule early so you can set a realistic start date with your contractor.